Trail Under Construction - Updated January 2008
The Environmental Assessment Worksheet effort
conducted by the Minnesota DNR was completed in early October 2007. The DNR determined that an Environmental
Impact Statement was not required.
The DNR gave the Chapter the OK to resume trail building. A rigorous trail construction effort
commenced in early October by Chapter members and the Minnesota
Conservation Corps. Segment HC1B
was completed in the fall of 2007.
NCTA Map MN-10
Total miles from
Steamboat Pass to Spider Coon Trail 9.1 miles
|
Section/Segment HC1C
As a result of the Environmental Review by the DNR, the route in
this segment paralleling the Schoolcraft
River may be
modified.
|
|
Defined: HWY 4 to Schoolcraft River
Bridge – Distance
to be determined. (50 yard segment
of Potlatch
Land)
|
|
Task
|
Completion Goal
|
% Complete
|
|
Pre-Flagging, Map Research, Flagging,
|
4Q06
|
100%
|
|
Walk, Gain Approval
Land Mgr.
|
4Q06
|
100%
|
|
Chain Sawing, mowing
|
3Q08
|
15%
|
|
Brushing, Limbing, Width & Height
Clearance Estab'd
|
3Q08
|
15%
|
|
Preliminary, Generic Trail Head Signs
posted
|
3Q08
|
15%
|
|
Tread way, remove toe stubbers, roots;
benching, final pass
|
3Q08
|
15%
|
|
Mowing
|
3Q08
|
15%
|
|
Blazing
|
3Q08
|
-
|
|
Apply for Certification
|
3Q08
|
-
|
|
Certification Received
|
4Q08
|
-
|
|
Erect all NCT signs
|
3Q08
|
-
|
|
Section/Segment HC1D – on hold pending DNR approval
|
|
Defined: Schoolcraft River
Bridge to Spider Coon Trail –
Distance to be determined
|
|
Task
|
Completion Goal
|
% Complete
|
|
Pre-Flagging, Map Research, Flagging,
|
4Q06
|
100%
|
|
Walk, Gain Approval
Land Mgr.
|
4Q04
|
100%
|
|
Chain Sawing, mowing
|
4Q08
|
-
|
|
Brushing, Limbing, Width & Height
Clearance Estab'd
|
4Q08
|
-
|
|
Preliminary, Generic Trail Head Signs
posted
|
4Q08
|
-
|
|
Tread way, remove toe stubbers, roots;
benching, final pass
|
4Q08
|
-
|
|
Mowing
|
4Q08
|
-
|
|
Blazing
|
4Q08
|
-
|
|
Apply for Certification
|
4Q08
|
-
|
|
Certification Received
|
4Q08
|
-
|
|
Erect all NCT signs
|
4Q08
|
-
|
|
Section/Segment HC1E – Under Construction 2006
|
|
Defined: East Boundary of Park to Spider Coon Trail 3.8
miles
|
|
Task
|
Completion Goal
|
% Complete
|
|
Pre-Flagging, Map Research, Flagging,
|
2Q06
|
100%
|
|
Walk, Gain Approval
Land Mgr.
|
2Q04
|
100%
|
|
Brushing, Limbing, Width & Height
Clearance Estab'd
|
2Q06
|
40%
|
|
Blazing
|
3Q08
|
-
|
|
Apply for Certification
|
3Q08
|
-
|
|
Certification Walk
|
3Q08
|
-
|
|
Certification Received
|
4Q08
|
-
|
|
Erect all NCT signs
|
3Q08
|
-
|
|
|
|
|
|
Links to Itasca Moraine
Chapter Pages